Friday, 28 January 2011

The fireplace grows up a little

Here's what the fireplace looks like a day later.  Our mason had to make an adjustment to some of the coursing so that slowed him down a bit.  Isn't it the cutest little fireplace in the whole wide world? 






He's gone back to his family for a week but will be back the week after next to continue building.

Thursday, 27 January 2011

Tenants' bathtubs are in; windows are bricked; construction begins on the fireplace

We've been getting hammered by snowstorm after snowstorm here, which makes it really hard to do any of the remaining outdoor work...and I hear that we're in for another set of flurries next week too.  It's torture waiting for weather that's warm and clear enough to put in the headhouse windows.  Look how much snow is piled up on the roof.



The tenants' bathtubs have been installed, and some of the framing around them put in.  I absolutely love how those bathrooms are turning out.  They feel really spacious for basic bathrooms and the tubs are wonderfully deep.



The plumbers have also run the rough plumbing for the tenants' toilets, sinks and their washers and dryers.  Lookin' good!


Our wonderful mason has been putting in brutally long days for the past week and a half, bricking in the dozen or so windows.  He's done now, except for a little part of one window. (The HVAC guys have been crawling through that space to install pipes in the back corner of the building.)  Here's what it looks like.  I'm so impressed with the way he angled the bricks to fill in the arch.  It's too bad it's going to be covered up with insulation and drywall.


Today he starts to build our fireplace!  I took a few "before" pictures, with all the bricks laid out for the firebox.



I'll keep you posted as it shapes up.

Friday, 21 January 2011

The headhouse windows are here...plus brickwork

We were out of town for a few days this week but in our absence the headhouse windows and French doors were delivered.  They're stacked in the building because it's been snowing/raining.  When the weather clears up it will be exciting to see them go in.





Also this week, our mason has been bricking up the inside of the windows on the back of the building.  He is doing an absolutely beautiful job.  Check it out:


Thursday, 13 January 2011

Progress, but it ain't pretty

I feel guilty about the light posting.  I keep hoping that if I hold off, I'll have something pretty to show you.  But it ain't pretty, so I'm giving you a few glimpses of what we've got going on inside the building.

Most exciting to me this week is the fact that we finally have the steel post installed between the master bathroom/bedroom.  This is the structural support we need to put in a massive glass wall (9 feet tall and about 10 feet long) between the two rooms and not have the garden and garden room come crashing through our ceiling.  Voila, the much-anticipated post:



The last photo shows the view from the far corner of the bedroom back towards the walk-in closet/alcove.  The opening is oversized.  It's actually going to have 2 pocket doors front and center that slide open to reveal the alcove and then slide closed to meet in the middle of the opening.  The closet feels wonderfully huge at this point, but I'm sure that will change when the drywall and shelves go in.

In other news, the HVAC installation continues, with ducts and equipment running pretty much everywhere now.  Here's the compressor that's in the wall/closet space between the two guest bedrooms, plus pics of its intake openings in the hallway on the third floor and in the ceiling of the second floor.




The last photo I have to share is one showing the framing for the concrete hearth that will form the base for the fireplace in our living room.


We're still torn between the wood mantel and the marble mantel.  Since both are beautiful, it's coming down to a question of size.  The wood one needs 6 inches of non-combustible material lining each side of the opening, which reduces the space for firewood to pretty puny dimensions (24 inches).  The marble fireplace, on the other hand, whose opening is 35 inches, carries no such requirements and might actually be able to be enlarge by a couple of inches at the top.  Our master mason (my boyfriend's godsend nephew from Milwaukee) is coming to town for two weeks on Sunday night, so we've got to make a decision stat.

Room framing continues in the basement.  Our poor crew spent the early part of the week sawing out the 3 foot deep granite foundation so that we could run the plumbing pipes closer to the outer wall of the building.  The work looked brutally hard (I dropped by during the sawing and fled the building in a cloud of dust, plus there were rueful comments about soreness the next day).  We're so glad we had it done, though, since it's going to make the bathrooms a much more respectable 8 feet by about 6.5 feet.  Since we were tweaking the size of the bathrooms anyway, I decided to put in really nice soaker tubs.  My priority was to get the deepest model available, with the cleanest inside shape.  It's shockingly difficult to find a deep tub with otherwise relatively small proportions!  (Ahem, bathtub manufacturers, you might want to make a note.)  The best I found was the Kohler Underscore (66" long x 36" wide x 22"deep).



Two have been delivered and are sitting in their boxes in the basement.  We're going to tile around them with our 3x6 Carrera subway tile.  Do I even need to say that I'm very excited to see how it looks?

Wednesday, 29 December 2010

HVAC is 50% in and we have electricity

The big news of the past 2 weeks has been the arrival of the HVAC subcontractor and his crew.  So far, they've put in about half of the equipment and ductwork.  I never thought I'd be so happy to see the beginnings of a utility room and these kinds of boring basement "bits".



Also, the carpenters have been putting in more of the basement walls.  Here's what our basement looked like when work stopped for Christmas: 




Quite chaotic with all the 2 by 4s.  One big change has come from seeing the rooms carved up down there.  We've decided to make the two bedroom unit a one bedroom instead.  It just looked too tiny and cramped with the two bedrooms and their closets roughed in.  Hard to imagine getting beds into the rooms and, with rooms that size, I can't imagine attracting any tenants other than kids just out of college.  Definitely not our target demographic.  So we're going to merge the two bedrooms into one and settle maybe for slightly less rent, but hopefully end up with someone more responsible and quieter - key, since we'll be living above them.

We were on-site today to meet with our bank's representative who evaluates the progress in order to direct them how much of our construction loan to disburse.  This is our first "draw" from that loan since we began the project a year and a half ago (we've been paying everything out of pocket).

While there, the NSTAR guys and police detail showed up to dig up the street and bring in our electric service.  Hooray!  That will be our third and final dig of the street and will give us the full complement of utilities in the building.  The sprinkler guy is the next utility to begin piping (after the HVAC), then it's the plumber and, last, the electrician. 

Wednesday, 8 December 2010

Mr. Smith goes to Boston

I am beyond excited: my boyfriend and I scored the Craigslist find of the decade.  Really.  (And I had thought those marble fireplaces were impressive.) 

I have been stressing a bit about finding the perfect sofa for our new place.  In my previous apartments, I'd been using a sweet silk upholstered antique settee that I'd found at Brimfield, but when I moved in with my boyfriend last year, it stayed in storage pending our move into the RBB and we began sharing his couch, which is *both* uncomfortable *and* ugly.  (In its defense, he doesn't think it's uncomfortable and I concede that it could be much uglier.)  I keep thinking about how the RBB's "great room" is going to need at least one but more likely two sofas.  Knowing what I like isn't a problem: a really high quality traditional English style deal with low, thin arms, attached back cushions, loose *down-filled* seat cushions, turned wooden legs and *sigh* casters (I have a bit of a caster fetish).  In other words, I wanted a George Smith sofa.  But of course $13,000-15,000 for a sofa ain't gonna happen and even at one of their floor sample sales the couches still seem to run between $6,000 and $8,0000.  Gulp.  Occasionally, a used one will pop up on eBay, more often in the UK than here, and when I lived in London I fondly tracked several, only to give up in frustration when the bidding went too high (about $4,000-5,000). 

So imagine my shock when I'm cruising Craigslist about ten days ago and I see a post for a George Smith sofa...for $250!!!  I literally didn't believe my eyes.  Immediately, I began imagining all the things that could be wrong with it.  The only things I could tell that were less than ideal about it were that it was way out on the Cape, practically all the way to Provincetown, which is nearly a two and a half hour drive each way from here, and that, under its worn white slipcovers, the upholstery was grass green, which is definitely not my favorite color.  Which is to say, there was absolutely nothing wrong with it.

Firing off an email, I began checking my inbox obsessively for a reply, all the while telling myself that my note would be buried amid a barrage of 200 other emails and that I'd never hear from the seller.  But then I did.  There followed a series of hiccups, each of which had me convinced that it was end of the trail and that I never would make the acquaintance of Mr. Smith, as the couch quickly became known.  These hiccups included the seller canceling his first planned trip to the area to sell the sofa out of the locker where it was being stored, the emergence of a rival buyer who had also offered the full asking price sight unseen, and a request for an agonizing "best and final offer" (which ultimately proved unnecessary because they other buyer withdrew).  I was so certain that this Craigslist sighting of the mythic sofa was too good to be true that I didn't even think the sofa could be mine, in case things fell apart. 

But with great joy and relief, I can now say that the sofa has pride of place in our rental house's kitchen.  (Don't ask: the back door, which leads into the kitchen, is the only one with a frame width of more than 30 inches and none of the interior doors are that wide.  We had to remove the casters to squeak it into the house but can't move it into another room.)






Mr. Smith even has a great back story: he's a movie star manque.  He was bought for the set of John Hughes' Baby's Day Out but never used which, given the reception of the movie, is probably for the best.  His slips are currently in the washing machine but I plan to spend the entire evening in the kitchen, not cooking.

We have a basement subfloor! And some kitchen framing





 I stopped by the building today since it sounded over the phone like there had been some progress at the RBB yesterday, particularly with the pouring of the basement subfloor.  When I arrived, yes, the concrete sub had come and gone, leaving us with a gorgeous smooth, *clean* basement floor!  It's very exciting to get to this stage after about 6 months of waiting. 

(In fairness, not for the concrete subcontractor but for the utility companies to dig up the street and bring in the necessary pipes.  So far we have water/sewer/sprinkler and gas but are still waiting for the electricity company to get their act together, which doesn't require that we hold off on the concrete.)

On Friday, our GC's crew of carpenters roughed in the kitchen framing in one of the tenant's units.  The last photo above shows the staircase the view down into the basement from the top of the staircase that tucks behind the unit's kitchen.  Here's the current state of affairs on the upper level of that unit:



The platform that wraps around the staircase is where the open concept kitchen is going to be.  The rest of the space is living room.  The random four panel door in the photo is for the unit's second means of egress, which is from the platform that's 3/4 of the way down the staircase out onto the (sloping) street.